casesConstruction - 6The Longest Mile: Nearly a Mile of Curbs and Gutters Removed and Replaced. Dispute Over Which Contractor was at Fault. The dispute in this case involved nearly a mile of improperly installed concrete curbs and gutters in an upscale residential development. We represented the contractor who installed the curbs and gutters. The other party in this matter was the paving contractor. The controversy was over which contractor was at fault for the defective work.
The paving contractor contended that our client did not follow the staking when it built the curbs and gutters and, therefore, it should not have to pay for the work. (The paving contractor itself did the surveying and staking.) Our client contended that it installed the curbs and gutters in accordance with the staking provided by the paving contractor, and that the paving contractor committed errors in surveying and staking. Our client and the paving contractor agreed to settle their disputes in binding arbitration, as opposed to a lawsuit. After a three-day arbitration hearing, the Arbitrator ruled in favor of our client, and awarded $135,957 in damages, attorney fees and costs.
|
Phoenix Office: 11240 North Tatum Boulevard, Suite 110, Phoenix AZ 85028 (602) 971-4800 Tucson Office: 3573 E. Sunrise Drive, Suite 215, Tucson, AZ 85718 (520) 615-3100 Copyright © 1999-2009 Loose, Brown & Associates, P.C. All rights reserved. |